Pul-E-Khumri 220KV Substation’s Transformer Extension Bey and Double Circuit Transmission Line
Pul-E-Khumri 220KV Substation’s Transformer Extension Bey and Double Circuit Transmission Line
This project aimed to expand the transformer bay at the Kar Kar Substation and construct a double circuit 20KV transmission line that spans 16 km from the Kar Kar Substation to Kelagai Base. Shahab Niru Company started the project in October 2020, and the US Army Corps provided the funds.