Kabul North-west 110/15 KV Substation

The project is in the northwest of Kabul city, and the owner of this project is the Ministry of Energy and Water (MEW). The project’s prime contractor was Safa Nicu Company. The Installation of indoor and outdoor equipment, including structures with complete testing and commissioning of the substation, was included in our scope of work. The construction and erection works were started in June 2007, and finally, the substation was commissioned in May 2009.