Mahipar 10/110 KV Substation
The project is located east of Kabul city, and the total capacity of this power plant is about 80 MW. The owner of this project is the Ministry of Energy and Water (MEW), and the prime contractor was SIEMENS. Dismantling old equipment and installing new indoor and outdoor equipment, including structures, were included in our scope of work. The construction and erection works were started in January 2014, and finally, the substation was commissioned in August 2014.